pe-9(1) |
power equipment and cabling | redundant cabling |
|
|
assessment objective: Determine if the organization: |
|
pe-9(1)[1] |
defines the distance by which redundant power cabling paths are to be physically separated; and |
|
pe-9(1)[2] |
employs redundant power cabling paths that are physically separated by organization-defined distance. |
|
potential assessment methods and objects: Examine: [select from: Physical and environmental protection policy; procedures addressing power equipment/cabling protection; facilities housing power equipment/cabling; other relevant documents or records]. Interview: [select from: Organizational personnel with responsibility for protecting power equipment/cabling; organizational personnel with information security responsibilities]. Test: [select from: Automated mechanisms supporting and/or implementing protection of power equipment/cabling]. |
||